Boat park Slip Resurfacing Project Day 5
8th September
Complete preparing cut out at bottom of the slipway.
Install shuttering.
Pour and lay concrete for one 4m x 5m bay.
Drill holes and install dowel tie in bars.
Complete preparing cut out at bottom of the slipway.
Install shuttering.
Pour and lay concrete for one 4m x 5m bay.
Drill holes and install dowel tie in bars.